Project Information
-
Project Name Testing and commissioning of the stormwater drainage project in the city of Jeddah at UP-03
-
End Client Jeddah Muncipality
-
Main Contractor Al Rashid Al Hak Saudi Company LTD
-
Location Jeddah
-
Scope of Work Installation of DN2000 mm reinforced concrete Jacking pipe lined with HDPE
-
Total Length Executed 249.35 linear meters
-
Start Date 06 Feb 2020
-
Completion Date 12 Apr 2020
Project Facts:
- The project area was close to the king's palace gate.
- The Project is close to the coast of the Red Sea and water table level encounter at 1-meter depth. (Some shaft's water pressure was around 1.5 bar)
- Due to water pressure the tunneling machine and string of pipes were moving backward.
- The project startup concurrent with Corona pandemic and subsequently lockdown and curfew.
Critical Success Factors:
- A special ancillary (Pipe Brake) was supplied to stop backward movement, enhance processes, boost job productivity, and improve compatibility with working
- Provided a suitable team of well-experienced staff.
- STCC team obtained special permits to work 24hours/7days
A pat on the back:
An appreciation letter has been awarded to STCC by Louis Berger-project consultant to appreciate the excellent work executed by STCC, also, Jeddah Municipality announced the great achievement through social media (Jeddah Municipality X platform and snap chat).