Project Information
-
Project Name Construction of a treated water line from King Abdullah Financial District to Princess Noura University.
-
End Client National Water Company (NWC)
-
Main Contractor Cesra Company Ltd.
-
Location Riyadh City
-
Scope of Work Welding & Installation of Ø34-inch steel casing pipes, then insertion of DN600 mm ductile iron pipes inside casing underneath several roads, (9 locations).
-
Total Length Executed 638 linear meters
-
Start Date 20 Feb 2015
-
Completion Date 29 Sept 2015
Project Facts:
- This project was started concurrently with the RIYADH METRO project, the client had a very limited time frame to complete this project (6 months) which was considered relatively a short period to complete the awarded scope of work.
- The client had requested at least two Microtunnelling subcontractors to execute this project because of the above reason and since the crossing is located in different areas with required inter-area movement and permits.
Critical Success Factors:
- Provided a suitable team of well-experienced staff.
- Working nonstop 24hours/7 days.
- Supply and provide more than setup equipment to work a head in more than one location.